How to Install and Position a Monitoring Prism for Total Station Monitoring Malaysia
How to Install and Position a Monitoring Prism
Correct installation is important when using a fixed monitoring prism for repeated total station observations.
A monitoring prism that becomes loose, changes orientation or is installed in an unsuitable position can affect the consistency of monitoring measurements.
The Myzox TK-10S / TK-10 Monitoring Prism L-Bar Type is designed for fixed monitoring applications and provides X/Y directional adjustment to help surveyors establish an appropriate target orientation.
This guide explains the main factors to consider when planning a monitoring prism installation for structural and deformation monitoring in Malaysia.
MTM Precision Sdn. Bhd. is an authorized distributor of Myzox in Malaysia.
Step 1: Determine the Monitoring Objective
Before installing any prism, determine what needs to be monitored.
Typical applications include:
Building movement
Retaining wall movement
Bridge deformation
Slope movement
Deep excavation
Structural displacement
Construction-related movement
Infrastructure deformation
The monitoring objective influences where targets should be positioned.
Step 2: Select the Monitoring Point
The prism should be installed at a location that represents the point the project team intends to monitor.
Depending on the structure, this may be on a:
Concrete wall
Building façade
Structural column
Retaining structure
Bridge element
Other suitable fixed surface
Monitoring point selection should follow the project's surveying and engineering requirements.
Step 3: Check the Mounting Surface
The prism needs a secure installation.
Before installation, check whether the selected mounting surface is suitable and stable.
Avoid locations where the mounting point itself may become loose or damaged independently of the structure being monitored.
A monitoring system is only useful when the target represents the intended structural point.
Step 4: Consider Total Station Line of Sight
Before fixing the prism permanently, confirm that it can be seen from the intended total station observation location.
Ask:
Is the prism visible?
Will future construction block the view?
Could scaffolding obstruct it?
Could temporary structures block the line of sight?
Will parked machinery or equipment create problems?
Can the total station observe the target from a stable position?
A monitoring prism that becomes permanently obstructed cannot serve its intended purpose effectively.
Step 5: Orient the Prism Toward the Total Station
The prism should be suitably oriented toward the total station.
The Myzox TK-10S / TK-10 provides X/Y directional adjustment, allowing the surveyor to adjust the target orientation during installation.
This is particularly useful when the mounting surface does not directly face the total station.
Correct target orientation helps establish suitable observation geometry.
Step 6: Secure the Monitoring Prism
The prism should be firmly attached according to the intended installation arrangement.
Once installed, check that the assembly does not move under normal site conditions.
The target should not be treated like a temporary survey accessory.
For monitoring work, it becomes part of the measurement reference system.
Step 7: Assign a Monitoring Point ID
Every prism should have a clear identification number.
For example:
MP01 – Building North Wall
MP02 – Building East Wall
MP03 – Retaining Wall Section A
MP04 – Retaining Wall Section B
MP05 – Bridge Pier
Clear identification reduces the risk of mixing up targets during repeated observations.
Step 8: Confirm the Prism Constant
The Myzox TK-10S / TK-10 has a specified:
Prism Constant: -25 mm
The appropriate prism setting should be configured in the total station according to the instrument manufacturer's instructions.
This should be checked before establishing baseline measurements.
Using inconsistent prism constants between observation sessions can introduce systematic measurement differences.
Step 9: Establish Stable Survey Control
A monitoring prism is only one component of the monitoring system.
The total station must observe the prism relative to stable survey control.
Reference points should be located appropriately so that movement of the control network does not become confused with movement of the monitored structure.
A typical arrangement is:
Stable Reference Points → Total Station → Monitoring Prisms
Both sides of this measurement relationship matter.
Step 10: Record the Baseline Measurement
Once installation and survey control have been checked, establish the initial measurement.
This becomes the baseline.
Record information such as:
Monitoring point ID
Coordinates
Elevation where applicable
Date and time
Instrument used
Prism model
Prism constant
Observation station
Relevant site notes
Future observations can then be compared against this reference data.
Step 11: Photograph the Installation
Photographs can be useful for documenting monitoring points.
A site record can include:
Overall location photograph
Close-up of the prism
Monitoring point ID
Orientation
Nearby reference features
This helps future survey crews identify the correct target and recognize whether the installation has been physically disturbed.
Step 12: Repeat Measurements Consistently
Monitoring is based on comparison.
Where practical, repeated observations should follow a consistent procedure.
For example:
Baseline → Week 1 → Week 2 → Week 3 → Week 4
or
Pre-Excavation → Excavation Stage 1 → Stage 2 → Stage 3 → Completion
Maintaining consistent measurement procedures helps improve the usefulness of comparisons between observation periods.
Where Should You Avoid Installing a Monitoring Prism?
Avoid locations that are likely to:
Be demolished during construction
Become hidden behind scaffolding
Be covered by temporary structures
Be frequently hit by machinery
Experience unrelated local movement
Become inaccessible
Lose line of sight
Be intentionally modified during construction
Thinking about future site conditions during initial installation can prevent monitoring problems later.
What Happens If the Prism Is Knocked?
A physically disturbed prism should not automatically be treated as if it still represents the original baseline point.
If the prism has been:
Hit
Loosened
Rotated
Removed
Reinstalled
Damaged
the monitoring team should inspect the installation and follow the project's procedure for handling a disturbed monitoring point.
Simply measuring it again and comparing it directly with the old baseline could produce misleading results.
What If the Prism Is No Longer Visible?
Construction sites change continuously.
Scaffolding, hoarding, cranes, temporary structures and equipment can block line of sight.
If a target becomes obstructed, the survey team should assess alternative observation arrangements according to the monitoring plan.
This is why visibility throughout the expected project duration should be considered before installation.
How Many Monitoring Prisms Should Be Installed?
There is no fixed number suitable for every project.
The required number depends on:
Structure size
Monitoring objective
Expected movement
Project geometry
Observation distance
Required coverage
Engineering requirements
Visibility
Large retaining walls, buildings or infrastructure structures may require multiple targets.
Myzox TK-10S / TK-10 Specifications
SpecificationDetailsModelsTK-10S / TK-10TypeMonitoring Prism L-Bar TypePrism Diameter1 inch / 25 mmPrism Constant-25 mmPrism Height60 mmBeam Deviation5″DimensionsH90 × W86.5 × D30 mmWeightApprox. 207 gAdjustmentX/Y direction
The compact L-bar design is well suited to fixed monitoring points where a conventional prism pole setup would be impractical.
Common Monitoring Prism Installation Mistakes
Several practical mistakes can reduce monitoring consistency:
Incorrect Prism Constant
Always confirm the prism setting before measurement.
Poor Target Orientation
Make sure the prism is suitably oriented toward the total station.
Weak Mounting
A loose target cannot provide a reliable fixed monitoring point.
Poor Line of Sight
Consider how the site will change during construction.
Unstable Survey Control
Reference points must also be suitable for monitoring work.
No Point Identification
Clearly label and document every target.
No Baseline Records
Without reliable initial observations, future comparisons become more difficult.
Monitoring Prism Installation Checklist
Before accepting a monitoring point, confirm:
Monitoring location selected correctly
Mounting surface suitable
Prism securely installed
Prism orientation checked
X/Y adjustment completed where required
Total station line of sight confirmed
Prism constant confirmed
Point ID assigned
Location photographed
Baseline measurement completed
Reference control verified
Monitoring record created
Applications for Myzox Monitoring Prism
The TK-10S / TK-10 can support:
Building movement monitoring
Retaining wall monitoring
Bridge monitoring
Slope monitoring
Deep excavation monitoring
Structural deformation monitoring
Construction monitoring
Infrastructure monitoring
Myzox Monitoring Prism Supplier in Malaysia
MTM Precision supplies Myzox monitoring prisms, surveying accessories and total station equipment in Malaysia.
We support surveyors, contractors, engineering consultants and monitoring professionals requiring equipment for repeated deformation and movement measurements.
MTM Precision also provides total station calibration and surveying instrument service in Malaysia.
Contact MTM Precision
MTM Precision Sdn. Bhd.
Myzox Authorized Distributor in Malaysia
Showroom & Service Centre
No. 29-1 & 29-2, Jalan Bandar 18,
Pusat Bandar Puchong,
47160 Puchong, Selangor, Malaysia.
Website: www.mtmpre.com.my
Email: mtmpre@yahoo.com
WhatsApp: +6016-6607346
Contact MTM Precision for Myzox TK-10S / TK-10 Monitoring Prism price, availability, installation enquiries and surveying equipment support in Malaysia.
Aug 18,2026